About the project

WASTEWATER TREATMENT PLANT IN SWEDEN

A municipal wastewater treatment plant in Sweden initiated a project to upgrade its existing ozone setup, increasing capacity and renewing the installation as part of a dedicated sidestream process for sludge water treatment. The project was driven through the early stages together with Christian Berner, supporting the utility with project documentation, planning, and specification work to prepare for a forthcoming tender process for expansion of the current setup.

The application builds on established full-scale operating experience showing that controlled ozonation of activated sludge sidestreams can improve settling properties and help mitigate operational issues associated with filamentous bulking.

WHAT THE CLIENT NEEDED

A COMPACT, RELIABLE OZONE SOLUTION

The plant required a compact and operationally safe ozone solution that could be implemented with minimal disruption to an operating facility. The project team chose a complete containerized solution to avoid constructing a new building and to simplify on-site implementation, targeting an ozone capacity of 1 500 g O₃/h, and supported by a structured execution plan.

Key deliverables include P&ID and functional description, approved drawings, defined FAT activities, delivery logistics, commissioning/inspection, operator training, and full documentation for handover and long-term maintenance.

THE SOLUTION

CONTAINERIZED OZONE, COMMISSIONED IN 3 DAYS

ULTRAAQUA supplied an ULTRAQUBE-18 SS system as a complete, containerized ozone plant designed to be integrated into municipal operations with minimal on-site complexity. The container setup consolidates core ozone generation and controls as a pre-assembled and factory-tested solution prior to delivery, incorporating the critical components needed to support fast deployment and reduced installation requirements on site. This approach was essential to ensure an efficient route from delivery to start-up and to minimize interfaces during commissioning.

Following the delivery, the installation and commissioning team completed the on-site scope in under three days, from delivery to final inspection. This ensured a fast, predictable handover to operations with minimal disruption to the running facility.

The ULTRAQUBE concept used for this project is modular, allowing the ozone capacity to be configured to the required duty point and providing a straightforward path for future scaling if treatment needs change. In parallel, the delivery scope emphasized predictable and safe operation in an operational wastewater environment, supported by clear operating procedures and an operations and maintenance framework for reliable day-to-day use.

To align with the project time plan, implementation was organized from contract and start meeting through project documentation, P&ID development, approved drawings, assembly and FAT in Denmark, delivery to Sweden, commissioning/inspection, and training of operating personnel, concluding with complete documentation for handover.

PRODUCTS APPLIED

UV SYSTEMS APPLIED

ULTRAQUBE™ 6-48 (SS) SERIES

Compact, robust ozone solution for large-scale industrial water flows.

Learn more

MORE CASES

Want to learn more?

Get in touch with us here. We strive to get back within 24 hours on all inquiries.

E-mail our engineersWe will get back to you within 24 hrs.
E-mail us24h reply